Completion Certificate to obtain approval from Muscat Municipality of some elevation changes of materials and increases of height of the building. As per Municipality rules all changes must not goes out of the previous agreement, unless all the changes must be rechecked, so we as a main consultant of this project we have to prepare all the drawings and request comes from the municipality.
Replacing Glass From the canopy side to ACP cladding, while the glass was just acting as an architectural façade design. As per the client request in to make the project running faster as well as reducing the cost and give massive look at exterior wise.